Friday 27 August 2010

NEW home cinema

sorry about saying the last home cinema setup was the last i will upload the new one soon i have changed the subwoofer and i am using 2 pairs of RC80i's and the spendor S5e's we currently own. there is also a new reciever and some other new updates

Saturday 20 March 2010

Multimedia


this is the final home cinema system
sorry there are 3 pairs of speakers









Saturday 13 February 2010

Alternate Appliances


Here is an picture with the alternate appliance scheme

Friday 12 February 2010

Kitchen

As we haven't blogged in a long time i thought i would fill you in with info on the kitchen we are either going to get a B&Q or moben kitchen.

Appliances

Wednesday 11 November 2009

No Progress !!

Have been away in Malaysia on business and the reports from the UK is work is still at a stand still.. has been like that for 3 weeks now. I could not get an update from Epsom Builders so called All Foundations directly.. and Andrew Murfin told me that the work was due to start again "imminently" and would take around 2 weeks to complete. Cant wait to get Stage 1 finished and signed off.. so we can proceed to the brick work.

Friday 23 October 2009

Sign off of the stages

Just found out that my architect does not have the qualifications to sign off the buildstore stages ! Also neother the current builder or the possible replacement has either. I was a bit stuck but called John O'Toole the NHBC solo inspector and he said he could do that so we are back on track again.

Bricks Approved




Had a call from the architect saying that the bricks we submitted have been signed off. This is quite a red/creamy brick - with a handmade look - quite textured. I need to find a concrete slate coloured tile as the one submitted was a red mix and we are not sure we want that. Some samples of the brick above. Not sure what it will look like on our house yet - hopefully we will know in a few months time.