Wednesday, 16 September 2009

At last a response from the council

After a delay of almost 2 months we received approval from the planning department to start work again !!! I dont have this in writing yet just and email from Mark Wilson from Epsom Builders saying he had spoke to Jacey Yates and have been given a verbal go ahead. Apparantly the tree officer was happy with the revised foundation design providing we made some changes to the surface water drainage at the back of the house. This may involve putting in an additional soakaway. The builders have scheduled the foundation company to come back on site on 28th September. Lets hope we get going this time.

No comments:

Post a Comment